Status "Active":
A status indicating active work on the project - creation and decomposition of PIs (all new PIs are "not defined," when transitioning from "On hold," all PIs become "not defined").
From Active to On hold: Transition can happen at any time without specific conditions.
-
All PIs become "not defined."
-
Tasks in "Done" remain in the "Done" state.
-
Tasks in "To do," "Doing," and "Review" are removed from their stages.
From Active to Completed: Mandatory condition - all tasks are in the "Done" state.
-
Transition is prohibited if at least one PI is "not defined."
-
Status "On hold":
Transition to this status is manual. Work is paused.
From On hold to Active: No specific conditions for transition.
-
PIs return to "not defined."
From On hold to Completed: Transition is prohibited.
-
Status "Completed":
The transition to this status is manual. This status indicates that work on the project is finished. All PIs in this status are "defined."
A mandatory condition for transitioning to "Completed" status - all tasks are in the "Done" state, and all PIs are "defined."
From Completed to Active: No specific conditions for transition.
-
Reopening the project is allowed - everything returns to the same state in which it was completed, i.e.,
-
PIs are "defined."
-
Tasks are in "Done."
From Completed to On hold: Transition is prohibited.
-