Risks embedded in the system:
- There is no member with the necessary competence to execute this task.
- There is no member with the necessary competence to review this task.
- Completing this task requires competence that only one member possesses.
- Reviewing this task requires competence that only one member possesses.
-
The expected time estimate for this task is greater than the threshold of 16 hours.
- If the task is part of the stream, it is a medium risk.
- If the task is on the critical path, it is a high risk.